Background Job Scheduling for IP30 (RISTRA20)

$
0
0

Introduction

As soon as I'm done with my step-by-step reply to a discussion on the subject matter recently, I realized that this long reply comprising of several Screen-captures possesses the characteristics of a Document. So I thought of converting it into a Document, so that members will be benefited from this frequently asked query.

 

Topic dealt here is for IP30 (program RSITRA20), but this method is valid for other programs too for background scheduling.

 

Here we see, how to do:

 

Step1. Create IP30 Variant.

- Run IP30,

- Give your Plan (here it is ABC123 ) in the Maintenance Plan field   (Do not forget this step)

- Click Save Button and in the resulting screen give the Variant name,

- Optional:- Tick  Only for Background Processing and Save again.

1.jpg

 

So we have just created a Variant named TEST for IP30 .

 

Note:

This variant will not be available for changes in IP30 Tcode, because  'Only for Background Processing' has been ticked.

For changes of this Variant, you need to Run SE38, give RISTRA20 in Program field, select Variants radio button, and then click on Display,

ClickF4 help in Variant field  and click Change.

 

 

Step2.  Create Background Job - Run Tcode SM36

Give Job Name and click Start Condition (See Picture)

2.JPG

 

A pop-up is displayed.

Follow the steps 1 to 7 given in Picture .

(Here it is assumed that you want the RISTRA20 program to run at midnights of everyday)

3.JPG


Click SAVE again


You will be given a pop-up.

4.JPG

Enter ABAP Program Name (Here it is RISTRA20) and the Variant (we know it is TEST), and SAVE.

(Steps 1,2,3 in the above picture)

 

You will be here:

5.JPG

Do not do anything, Click Back arrow and


SAVE

 

All Done

 

Now to see the schedule -

Run SM37 and Execute. (Give Current Date as FROM date and Date after 2 days as TO Date)

Execute to see a screen like this, where your Job is seen scheduled to be run at Midnight of Every Day. (According to the settings in picture 3 above)

6.JPG

During Scheduling, the Status changes from Released to Active andafter Scheduling it turns to Finished.

Hope members will be benefited by this post.

 

Thank you

Jogeswara Rao K

 

 

This document was generated from the discussion: Job Scheduling and activate for Maintenance Plans and modified to be a Document for general relevance.